PLH GROUP PROJECT
Questar ML 3 Replacement
PROJECT SCOPE
The Questar ML 3 replacement project focused on the replacement of approximately 15 miles of 16” aging pipeline for Questar Pipeline.
The project began in March 2011 and was completed in October 2011. The project employed 160 personnel at its peak and managed a steep face of 45 degrees along with numerous sidecuts and lack of drivable access.

Oil and gas infrastructure contractor Snelson Co. a PLH Company replaced 15 miles of corroded pipeline for Questar Pipeline.